Two dates govern every Solution 2 project:

  • 180 days from grant execution: construction must begin, with at least one inspection documenting progress.
  • 365 days from grant execution: construction must complete, unless a written hardship extension is approved.

These aren’t targets. They’re the rules. Miss them without the right paperwork and you have a real problem — including the possibility that the program pulls funding for work that hasn’t happened.

Here’s how to keep the clock moving.

What “construction begins” actually means

“Construction begins” isn’t a handshake, a tear-out day, or a load of materials dropped in the driveway. It means:

  • Work has started on site in a way that shows visible progress, and
  • An inspection has been performed and documented.

That inspection documentation is what the program uses to verify that the 180-day window was met. Your contractor — and the program — should be coordinating that inspection deliberately.

Why projects miss the 180-day window

In our experience, three things blow the window:

1. Permit delay. The parish took longer than expected to issue a permit, or the permit came back with corrections. The fix: apply for permits immediately after grant execution, not after the Project Plan is “finalized.” Permits can run parallel.

2. Contractor backlog. You signed with a contractor whose calendar didn’t actually have a window for your project. The fix: before signing, confirm the contractor’s calendar. Ask specifically: “When can a crew actually be on my site?”

3. Scope ambiguity. The scope of work had enough ambiguity that you and the contractor couldn’t agree on what “start” meant. The fix: a line-itemed scope with clear milestones. “Start” is the first line item happening on your roof.

Keeping the 365-day window

The 365-day clock is longer, but it’s also not long. A gut-and-rebuild with multi-trade coordination can consume it quickly.

Keeping your project on the 365-day clock comes down to:

  • Early permitting — see above.
  • Pre-ordered long-lead items — some materials are still on extended lead times. Your Project Plan should identify them and the contractor should order them the day the contract is signed.
  • Deliberate draw scheduling — draws get released after inspections. If you bunch your draws in the last 90 days, you’ve bunched your inspection coordination in the last 90 days too, and any delay there cascades.
  • A contractor who runs the program, not the other way around — the program has rules. A contractor who understands them doesn’t get surprised by them.

Hardship extensions exist — but plan for not needing one

The program allows written hardship extensions past the 365-day window. They’re real and they’re granted when justified. But they’re not a substitute for running the project on schedule.

If your project is going to need an extension, you know it early — not at day 360. Flag it with your contractor and with the program as soon as you see it coming, and document the cause. Weather, material delays, and permit issues are all legitimate causes, but the program needs them in writing.

Our practice on the clock

Every Solution 2 project we run has three dates on the wall on day one:

  • Grant execution date — the start of the clock.
  • Day 180 — target for documented construction start. We aim for day 60.
  • Day 365 — target for construction complete. We build schedules against day 300 so we have 65 days of buffer for anything that goes sideways.

If a project requires longer than that, we say so before the Project Plan is signed — not after.

Further reading

Call us at (985) 255-2435 if you’re concerned about a window in your current Project Plan.